NORTH-CENTRAL BREAKDOWN: EIGHT ROADS
(1) DUALIZATION OF SULEJA-MINNA ROAD PHASE II (KM 40+000 – 101+000) IN NIGER STATE
Contractor: Salini Nigeria Ltd
Contract Sum: N36.2bn
Current Completion Level: 17.20%
2020 SUKUK Payment: N2.5bn
Road/Bridge Works
Kms Covered (2020): 14km
(2) ABUJA-ABAJI ROAD (SECTION 1: INTERNATIONAL AIRPORT LINK ROAD JCT – SHEDA VILLAGE JCT)
Contractor: Dantata & Sawoe
Contract Sum: N28.6bn
Current Completion Level: 96.11%
2020 SUKUK Payment: N1.0bn
PROJECT COMPLETION
Kms Covered (2020): 2.2km
(3) ABUJA-LOKOJA ROAD: SECTION IV (KOTON KARFE – LOKOJA)
Contractor: Gitto Construction
Contract Sum: N31.08bn
Current Completion Level: 76.0%
2020 SUKUK Payment: N2.5bn
Asphalt Wearing and 1st & 2nd Coat surface dressing on shoulders with lined drains
(4) DUALIZATION OF OBAJANA JUNCTION TO BENIN PHASE 2: SECTION 1 (OBAJANA JUNCTION TO OKENE)
Contractor: CGC Nigeria Ltd
Contract Sum: N30.56bn
Current Completion Level: 32.66%
2020 SUKUK Payment: N3.5bn
Ongoing Dualization works
Kms Covered (2020): 63.05km Covered (2020): 5.5km
(5) CONSTRUCTION OF OJU/LOKO-OWETO BRIDGE TO LINK BENUE & NASARAWA WITH NEW APPROACH ROADS
Contractor: RCC Nigeria Ltd
Contract Sum: N51.61bn
Current Completion Level: 96.7%
2020 SUKUK Payment: N6.0bn
PROJECT COMPLETION
Kms Covered (2020): 5.0km
(6) RECONSTRUCTION OF BIDA-LAPAI-LAMBATA ROAD IN NIGER STATE
Contractor: CGC Nigeria Ltd
Contract Sum: N33.3bn
Current Completion Level: 13.06%
2020 SUKUK Payment: N5.0bn
CH25+000 – CH35+500, CH43+600 – CH55+000 up to A/C Wearing Course
Kms Covered (2020): 20.9km
(7) RECONSTRUCTION OF MAKURDI-NAKA-ADOKA-ANKPA ROAD IN BENUE STATE
Contractor: Gilmor Engineering
Contract Sum: N27bn
Current Completion Level: 0.53%
2020 SUKUK Payment: N3.0bn
CH70+500 – CH58 (12.5Km), CH70+650 – CH150 (12.5Km) up to A/C Binder Course
Kms Covered (2020): 25.0km
(8) CONSTRUCTION OF ROAD LINKING BARO PORT TO GULU TOWN IN NIGER STATE
Contractor: GR Building Nigeria
Contract Sum: N10.61bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N3.0bn
PROJECT COMMENCEMENT
Kms Covered (2020): 7.75km
NORTH-EAST BREAKDOWN: EIGHT ROADS
(1) KANO-MAIDUGURI ROAD: (SECTION II – SHUARI LINK TO AZARE)
Contractor: Setraco Nigeria Ltd
Contract Sum: N65.31bn
Current Completion Level: 86.62%
2020 SUKUK Payment: N11.0bn
Ongoing Construction
Kms Covered (2020): 53.93km
(2) KANO-MAIDUGURI ROAD: (SECTION III – AZARE LINK TO POTISKUM)
Contractor: Mothercat Ltd
Contract Sum: N45.18bn
Current Completion Level: 91.79%
2020 SUKUK Payment: N2.0bn
PROJECT COMPLETION Kms Covered (2020): 0km – Toll Plazas/Weighbridges
(3) KANO-MAIDUGURI ROAD: (SECTION IV – POTISKUM LINK TO DAMATURU)
Contractor: CGC Nigeria Ltd
Contract Sum: N51.90bn
Current Completion Level: 80.51%
2020 SUKUK Payment: N4.0bn
Main Carriageway Works
Kms Covered (2020): 94.0km
(4) KANO-MAIDUGURI ROAD: (SECTION V – DAMATURU LINK TO MAIDUGURI)
Contractor: CCECC Nigeria Ltd
Contract Sum: N67.79bn
Current Completion Level: 50.94%
2020 SUKUK Payment: N4.0bn
Main Carriageway Works
Kms Covered (2020): 59.6km
(5) REHABILITATION OF GWOZA-DAMBOA-GONIRI-NGAMDU IN BORNO STATE
Contractor: Hajaig Construction Nigeria Ltd
Contract Sum: N34.60bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N3.0bn
Site Clearing/Earthworks, Culverts, Pavement & Surfacing
Kms Covered (2020): 15.0km
(6) RECONSTRUCTION OF MAYO BELWA-JADA-GANYE-TOUGO ROAD IN ADAMAWA STATE
Contractor: Triacta Nigeria Ltd
Contract Sum: N22.69bn
Current Completion Level: 14.14%
2020 SUKUK Payment: N3.0bn
Asphalt Wearing & Reconstruction
Kms Covered (2020): 42.0km
(7) CONSTRUCTION OF IBI BRIDGE IN TARABA STATE
Contractor: RCC Nigeria Ltd
Contract Sum: N57.07bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N2.0bn
Piles and Pile caps for Axis 2 & 3, 4 & 5 Ibi Side
Kms Covered (2020): Bridgeworks
(8) REHABILITATION OF NGURU-GASHUA-BAYAMARI
ROAD: SECTION II (GASHUA-BAYAMARI) IN YOBE STATE
Contractor: Ric Roc Construction Ltd
Contract Sum: N11.77bn
Current Completion Level: 0.14%
2020 SUKUK Payment: N1.5bn
Rehabilitation up to Asphalt Binder
Kms Covered (2020): 13.0km
NORTH-WEST BREAKDOWN: SEVEN ROADS
(1) KANO-MAIDUGURI ROAD: (SECTION I – KANO LINK TO WUDIL WITH LINK TO SHUARI)
Contractor: Dantata & Sawoe
Contract Sum: N55.1bn
Current Completion Level: 67.51%
2020 SUKUK Payment: N4.5bn
Interchange 1,2 & Carriageway
Kms Covered (2020): 58.0km
(2) DUALIZATION OF KANO-KATSINA ROAD: (PHASE 1 – KANO TOWN AT DAWANAU ROUNDABOUT TO
KATSINA STATE BORDER) IN KANO STATE
Contractor: CCECC Nigeria Ltd
Contract Sum: N14.0bn
Current Completion Level: 51.48%
2020 SUKUK Payment: N2.75bn
Ongoing Dualization
Kms Covered (2020): 57.0km
(3) CONSTRUCTION OF KADUNA EASTERN BY-PASS
Contractor: Eksiogulari Nigeria Ltd
Contract Sum: N38.19bn
Current Completion Level: 39.40%
2020 SUKUK Payment: N4.0bn
CH16+000 – CH37+000 (Road Works up to A/C Binder Course), Bridgeworks at Chikaji CH35 Kms Covered (2020): 21.0km
(4) CONSTRUCTION OF KANO WESTERN BY-PASS
Contractor: Dantata & Sawoe
Contract Sum: N22.77bn
Current Completion Level: 66.98%
2020 SUKUK Payment: N4.0bn
Asphalt Wearing; Bridgework (3 & 4); CH 0+425 – CH 9+030 Median Drain & Slope Protection (Bridge 2)
Kms Covered (2020): 12.47km
(5) DUALIZATION OF KANO-KATSINA ROAD: (PHASE II – KANO/KATSINA BORDER LINK TO KATSINA STEEL ROLLING MILLS ROUNDABOUT)
Contractor: CCECC Nigeria Ltd
Contract Sum: N29.65bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N3.75bn
Ongoing Dualization
Kms Covered (2020): 26.5km
(6) REHABILITATION OF SOKOTO-TAMBUWAL-JEGA-KONTAGORA-MAKERA ROAD: (SECTION I – SOKOTO / KEBBI STATES)
Contractor: Triacta Nigeria Ltd
Contract Sum: N30.45bn
Current Completion Level: 68.52%
2020 SUKUK Payment: N5.0bn
Carriageway Reconstruction
Kms Covered (2020): 40.0km
(7) REHABILITATION OF AJINGI-JAHUN-KAFIN HAUSA-ROAD IN JIGAWA STATE
Contractor: H & M Nigeria Ltd
Contract Sum: N25.03bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N2.5bn
Carriageway Reconstruction
Kms Covered (2020): 12.5km
More ongoing road projects on other geopolitical zones to be published later on Tropics Nigeria.
Abudulrasheed Mubarak is a freelance content creator. He starting his writing career in 2011. He is a graduate of Auchi Polytechnic, Auchi in Urban and Regional Planning.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.